|
Phase IV.2 construction works |
|
|
The construction works of the main waste water collector Kula – Vrbas, Phase IV.2 Ch. 8+061.40 km - 10+019.00 km in municipality of Vrbas were completed on 22 April 2010. From 22 - 30 April, the Contractor “Graditelj NS” shall carry out hydraulic testing of the pipeline and internal pipeline monitoring as required. Complete attestations for the in built materials will be ready by the 3 May 2010. If the weather allows the Contractor plans to complete site clearing works. The Technical acceptance is set for 1 May 2010.
|